SCE/Laguna Canyon Road Utility Undergrounding

The construction work will require portions of the outbound lane to periodically be moved to the center lane between 9:00 a.m. and 3:00 p.m., Monday through Friday, through September 24, 2016.  One lane in each direction is expected to be maintained open during most of this period.  This phase of the project includes the placement of SCE's underground cables, equipment, connecting properties and removal of SCE's overhead distribution system.  To avoid construction conflicts between SCE and other communications crews, Cox, Frontier, and other communications companies will schedule work after SCE has completed their work.  Information and scheduling will be provided on this final phase to the project in the next 2-3 weeks.